Inauguration of Da Nang International Passenger Terminal 3,500 billion VND '

On the afternoon of May 19, the Ministry of Transport, the People's Committee of Da Nang City inaugurated the International Passenger Terminal, Da Nang International Airport.
 
The project has an initial capital of VND 3,500 billion from the capital of socialization, not using the state budget.
The terminal consists of 4 main categories: international terminal, bridge over station and parking lot with total investment of 3,500 billion VND, built on land area of ​​21,000 m2 with floor area Is 48,000 m2; There are 40 check-in counters, 20 departure counters, 22 entry counters and 10 departure lounges.
 
In particular, the station is designed with a separate floor for commercial and non-air services, to meet the needs of passengers.
 
  
 
Cutting in the inauguration of the international passenger terminal
 
 
 Participating in the project include contractors with prestige and experience in the field of airport design and construction such as:
 
Design consultant contractor: CPG Consultants Pte Ltd, PAE Co., Ltd and design consultant company. This is a consortium that has done design consultancy for many passenger terminal projects in Vietnam.
 
Supervision consultant contractor: CONINCO Joint Stock Company for technology consultant, equipment and inspection
 
  
 
Technician Epower at the inauguration
 
Construction contractor: Epower Engineering Construction Co., Ltd - a prestigious contractor providing all aluminum roof, glass roof, anti-slip system on the roof, roof of the project, Bao Construction Joint Stock Company Ho Chi Minh Museum, Lanmak Construction Company, ATAD Steel Joint Stock Company, REE Refrigeration Mechanical Joint Stock Company ...
 
During the implementation of the project, the investor and the contractor have encountered many difficulties and challenges such as narrow construction site, both exploitation and construction, Due to climate change in 2016, the city has many long-lasting rains, raining up to 3 consecutive months. But with high determination and accumulated experience, aiming to bring the project to the right track on schedule. The investor has worked with construction contractors, consultants, quality control consultants and design consultants to mobilize all resources and capital, apply new technologies, and improve management skills. , The construction organization should have brought the project on time.
 
  
 
Da Nang International Airport inside the house
 
The international passenger terminal, when put into service, can serve 6 million passengers a year and can operate all types of aircraft, along with the VIP terminal, the apron and apron. The number of other modernly invested projects will create a new dimension for the Da Nang International Airport to attract domestic and international tourists, in time to best serve the Annual Summit Forum. Asia-Pacific Economic Cooperation - APEC 2017./.
 
  
Overview of Da Nang international passenger terminal 3,500 billion