To be able to do this border, the scaffolding has been enclosed around, only a measurement error careless workers will be forced to do again. E-power's implementation of the TH School project can be broken down into the following steps:
1. Measure the actual size of each home
2. Install gutter frame
3. Turn the gutter with stainless steel was installed at E-power's workshop on the roof, using the cutting machine, cut the right angle and weld the troughs together.
4. Technicians and site engineers check each weld to ensure all seals are sealed
5. Check the actual size of the aluminum cover
6. Aluminum plate processing
7. Paint the color of the processed sheet
8. Apply painted aluminum panels, finishing the roof edges.