After more than a year of construction with urgent and urgent progress, the Long Thanh airport passenger terminal has basically completed all the underground reinforced concrete and entered the roofing stage.
The Long Thanh international airport passenger terminal is considered the heart of the project with a stylized lotus petal design, including 1 central terminal and 3 petals, 1 ground floor and 3 floors with a total floor area of up to 376,400 m2
E-Power Construction Engineering Co., Ltd. is the unit in charge of constructing the PIER roof system (3 lotus petals) as well as the roof system of the telescopic bridge area. With experience in implementing a series of roof systems and covering systems of Tan Son Nhat, Noi Bai, Van Don, Da Nang, Phu Bai airports... E-Power is rushing every day to ensure the progress and quality of the project.
E-Power's technical staff is checking the quality of the panels under the witness of the TVGS unit
At the passenger terminal construction site in early 2025, the team of workers has begun installing the roof structure. Up to now, the terminal roof has been installed for about 3 spans, with an area of over 1,500m².
The roof system of Long Thanh airport terminal has 5 layers with complementary functions such as insulation, waterproofing, and surface protection to ensure durability. The top layer is a layer of aluminum profiles, connected together by the Clip system, without screws, so the roof system can withstand thermal expansion and harsh environmental factors. Each layer must be constructed according to the correct technical process, requiring high precision