Influence of traffic ground conditions on the construction of the Nhon - Hanoi Railway Station

Currently, along with the rapid development of the economy, Hanoi City is facing many urbanization problems including internal traffic problems. In order to solve the above problem, the Government is investing and constructing an elevated railway system in two major cities, Hanoi and Ho Chi Minh City, which is a fast, high-volume passenger transport system. Exploit effectively in most advanced countries and are being widely deployed in developing countries.
 
However, Hanoi is a densely populated area, many households still occupy hearts, roadsides to do business, concentrated intersections do not have bridges, tunnels for pedestrians .... As a result, the narrow streets became more crowded.
On the other hand, due to our management level, our strategic vision of urban planning is still very limited, unable to keep up with the daily urbanization rate, so we do not control planning well. architecture of civil constructions, traffic constructions. Consequently, the city center is now becoming crowded, narrow streets, cluttered houses with unscientific shapes and sizes, lack of entertainment areas ... Thus, when developing commencement of construction works, especially large-scale projects requiring large construction ground, the contractor will face many difficulties.

 
As the unit responsible for executing the entire structure of the project for the Nhon-Hanoi Railway Station, during the construction process, E-Power Construction Engineering Co., Ltd. faced with many difficulties:

- Nhon-Hanoi Station runs through two big intersections, Mai Dich and Cau Giay. These are 2 arterial roads north of the capital. With such traffic conditions, the possibility of obtaining a day-to-day circulation permit for vehicles transporting construction materials is extremely difficult, especially at rush hours. This will greatly affect the progress of construction works. Therefore, to meet the progress of the project, E-Power workers and employees do not hesitate to work overtime, night shift, cranes, construction plans and material gathering, ensuring that the construction process is not discontinuity.
 




- Frequent inundation in season in some streets may also affect construction (causing flooding of excavations, limiting the ability of pumping underground water, surface water, increasing the possibility of traffic congestion. .)
 
- The construction ground is narrow, so the area for storage, gathering machines, materials will be very limited. It is natural to gather materials in suburban areas far from the construction site. Construction machinery has a limited range of activities in space and time. Therefore, this is also an economic problem for E-Power when participating in the project.
 
- The characteristic of the enclosure is in the outside, in direct contact with the surrounding space, so it is very important to ensure the safety of vehicles participating in traffic for the construction process. E-Power always attaches great importance to safety issues: Participate in insurance and fully equip labor protection for workers, fully equipped with falling nets for stations, train and remind workers to improve their ideas. safe labor everyday, ...

 
In summary, there are many factors that affect the progress and cost of construction. However, in crowded and narrow cities, ground conditions, traffic conditions have a great influence, especially for the construction of works along arterial roads. With the professionalism and experience in handling problems arising under limited environmental conditions, E-Power Construction Engineering Co., Ltd. always offers the most optimal solutions, meeting the progress and quality. commitment.