Up to this point, contractors for the construction of Van Don International Airport (Quang Ninh) are urgently completing the final construction works at the railway station, air traffic control tower, service area, technical infrastructure around ... to prepare to put into operation, pick up commercial flights from early January 1.2019 (before Lunar New Year)
 
Phi trường Vân Đồn 7.500 tỉ đồng chuẩn bị khai thác các chuyến bay thương mại - Ảnh 1.
 
The 3.6 km runway can be landed and landed and the first calibration flight is scheduled for 1.7.2018. Photo: T.N.D
 
According to Hai, the representative of the investor (Sun Group) said that with the construction progress as calculated by the investor, after 15.10.2018, all ground items must be completed, then wait Licensing procedures go into operation.

Phi trường Vân Đồn 7.500 tỉ đồng chuẩn bị khai thác các chuyến bay thương mại - Ảnh 2.
 
Technical equipment at the 45 meter high tower has been installed. Photo: T.N.D
 
In order to ensure the timeliness of the project, the organization of the project is very urgent. On the site, the contractor mobilized hundreds of workers to work in three continuous shifts to perform the following items: installation of furniture for the station area, embellishment of the campus and surrounding infrastructure.
 
Phi trường Vân Đồn 7.500 tỉ đồng chuẩn bị khai thác các chuyến bay thương mại - Ảnh 3.
Van Don Airport has a capacity of receiving 2.5 million people per year, which is being used by industrial hygiene workers. Photo: T.N.D
 
It is the first airport in Vietnam invested by a private enterprise, operating at a cost of VND7,500 billion. Van Don Airport is considered a complex airport on an area of ​​325 hectares.

Phi trường Vân Đồn 7.500 tỉ đồng chuẩn bị khai thác các chuyến bay thương mại - Ảnh 4.
This airport scale is at the level of the International Civil Aviation Organization (ICAO) standards, meeting domestic demand and providing international flights with an initial frequency of 1,250. day / hour and designed capacity of up to 2.5 million passengers / year (phase I).

Phi trường Vân Đồn 7.500 tỉ đồng chuẩn bị khai thác các chuyến bay thương mại - Ảnh 5.
 
Many equipment and means of ground service have been gathered, waiting for the day to put into operation of specialists.
Photo: T.N.D
 
With a 3.6 km long runway, the modern navigational system of the world will be used to ensure the operation of large civil aircraft like the B777 and the equivalent in all weather conditions. Prior to this, from 1-16.7, this runway received flight safety calibration.

Phi trường Vân Đồn 7.500 tỉ đồng chuẩn bị khai thác các chuyến bay thương mại - Ảnh 6.
  
The entire yard of ice and signal lights were completed in early July. Photo: T.N.D  
 
Along with the 54km highway link connecting Ha Long - Van Don to prepare the traffic, Van Don International Airport when put into operation will be the center connecting the transport infrastructure when shortening the distance between Van Don with big cities of Vietnam and the world.
 
Phi trường Vân Đồn 7.500 tỉ đồng chuẩn bị khai thác các chuyến bay thương mại - Ảnh 7.
Transport infrastructure connecting localities with Van Don airport has been fully invested. Photo: T.N.D
 
Phi trường Vân Đồn 7.500 tỉ đồng chuẩn bị khai thác các chuyến bay thương mại - Ảnh 8.
 
Transport infrastructure connecting localities with Van Don airport has been fully invested. Photo: T.N.D
 
 
Phi trường Vân Đồn 7.500 tỉ đồng chuẩn bị khai thác các chuyến bay thương mại - Ảnh 7.
The 54-km-long Ha Long-Van Don expressway linking Hanoi-Hai Phong-Quang Ninh Expressway will provide convenient access for both road and air traffic. Photo: T.N.D
Phi trường Vân Đồn 7.500 tỉ đồng chuẩn bị khai thác các chuyến bay thương mại - Ảnh 8.
Quang Ninh province expects this to be the most important driving force for Van Don to become a green, smart, modern coastal city; dynamic economic development of new industries, high level, with focus on services, high-end tourism complex, modern entertainment industry with casino; high technology industry; Center of innovation, creation Northeast of the country ...